Operations & Projects

Our portfolio of tier-one assets provides exposure to copper, platinum group, zinc and other metals essential for the world’s transition to clean energy and a low-carbon economy. Our stakeholders benefit from long-life projects with low costs, low-capital intensity and leading ESG programs.

Democratic Republic of the Congo

Kipushi Zinc Mine

Ownership: Ivanhoe Mines 62%
Gécamines 38%

The Kipushi zinc-copper-germanium-silver-lead mine in the DRC is the world's highest-grade zinc mine. Construction of the new 800,000-tonne-per-annum concentrator facility was completed in May 2024 with first concentrate produced in June 2024. The concentrator includes dense media separation (DMS) and a milling and flotation circuit and is expected to produce more than 278,000 tonnes of zinc in concentrate over the first five years of production. Design recoveries are targeted at 96%, with a concentrate grade averaging 55% contained zinc. Kipushi’s 2024 production guidance is between 50,000 - 70,000 tonnes of zinc in concentrate.

Download 2022 Feasibility Study

35.34% zinc

Average grade over the first five years of production

800kt

Capacity per-annum of the new zinc concentrator

278kt

Production of zinc contained in concentrate over the first 5 yrs of operation

11.8 Million

Measured and Indicated Mineral Zinc Resources

50,000-70,000t

Kipushi’s 2024 production guidance is between 50,000 - 70,000 tonnes of zinc in concentrate

Ivanhoe acquired its 68% interest in the Kipushi Project in November 2011, through Kipushi Holding which is 100%-owned by Ivanhoe Mines. The balance of 32% in the Kipushi Project is held by the DRC state-owned mining company, Gécamines, whose ownership will increase to 38% upon completion of the conditions precedent to the updated joint venture agreement signed in late 2023.

The Kipushi mine is adjacent to the town of Kipushi in the DRC approximately 30 kilometres southwest of the provincial capital of Lubumbashi. It is a high-grade, underground zinc-copper project in the Central African Copperbelt which mined approximately 60 million tonnes grading 11% zinc and 7% copper between 1924 and 1993. In addition to producing copper and zinc, the mine produced 12,673 tonnes of lead and approximately 278 tonnes of germanium between 1956 and 1978. The mine had been managed on a care and maintenance basis since 1993. In late 2022, Ivanhoe and its partner Gécamines finalized an agreement to return Kipushi to production.

Underground development continues to open multiple access levels into the Big Zinc orebody, while decline development is well-advanced. As at December 31, 2023, 4,565 metres of lateral and decline development was completed for the project to date, and a total of 3,957 metres of horizontal development had been completed during 2023, approximately 20% ahead of schedule. Stope perimeter drives are being developed on the 1,245m, 1,260m, 1,290m and 1,320m levels, with stope access development at the 1,335-metre level is advancing well. Waste rock and low-grade mineralized rock from the advancement of the perimeter and access drives are being hoisted to the surface through Shaft 5 and stockpiled. Shaft 5 is planned to be the main production shaft with a maximum hoisting capacity of up to 1.8 Mtpa. The bottom of Shaft 5 provides primary access to the lower levels of the mine, including the Big Zinc orebody, along the 1,150-metre haulage level.

Approximately 336,000 tonnes of development ore stockpiled on surface at a grade of 23% zinc at the end of Q2 2024.  A total of 18,733 tonnes were mined at the 1,245m level, with an average grade of 18.7% zinc. Mining panels have been established between the 1,290-metre level and the 1,320m level.

Powered by renewable hydro-generated electricity, Kipushi is set to be among one of the world’s lowest Scope 1 and 2 greenhouse gas emitters per tonne of zinc metal produced and will be the world’s highest-grade major zinc mine, with an average grade of 36.4% zinc over the first five years of production.

Shaft 5

Shaft 5 is planned to be the main production shaft once operations commence, with a maximum hoisting capacity of up to 1.8 Mtpa. The bottom of Shaft 5 provides primary access to the lower levels of the mine, including the Big Zinc orebody, along the 1,150-metre haulage level.

De-bottlenecking program

Basic engineering has commenced on de-bottlenecking initiatives of the Kipushi concentrator, to target a 20% increase in processing capacity to 960,000 tonnes of ore per annum. The de-bottlenecking program is expected to take approximately nine months, based on the availability of long-lead order equipment.

Lowest greenhouse gas emitter

Kipushi will be the lowest greenhouse gas (GHG) emitter per tonne of zinc produced. On a Scope 1 and 2 basis (reported from ore to mine gate), Kipushi’s GHG emissions intensity for 2025 is expected to be 0.019 equivalent tonnes of carbon dioxide per tonne of contained zinc produced (t CO2-e / t Zn). This ranks Kipushi near the bottom of the Scope 1 and 2 GHG emissions curve.

Technical Reports

View document library
Kipushi 2022 Feasibility Study, February 2022
Kipushi 2019 Mineral Resource Update
Kipushi 2017 Pre-Feasibility Study, January 2018
Kipushi Project – Preliminary Economic Assessment NI 43-101 Technical Report, May 2016
Kipushi Project – Mineral Resource Estimate NI 43-101 Technical Report, January 2016

Recent Press Releases

View all press releases
Ivanhoe Mines and Gécamines Sign New Joint Venture to Restart the Ultra-High-Grade Kipushi Mine, a Century Since First Opening
Construction of new concentrator and underground development well ahead of schedule for first production in Q2...
Read more