Operations & Projects

Our portfolio of tier-one assets provides exposure to copper, platinum-group metals, nickel, zinc and other metals essential for the world’s transition to clean energy and a low-carbon economy. Our stakeholders benefit from long-life projects with low costs, low-capital intensity and leading ESG programs.

Democratic Republic of the Congo

Kamoa-Kakula Copper Complex

Ownership: Ivanhoe Mines 39.6%
Zijin Mining 39.6% | Crystal River 0.8% | DRC Government 20%

The Kamoa-Kakula Copper Complex, located in the Central African Copperbelt, is the world’s fastest-growing, highest-grade, and lowest-carbon emitting, major copper mine. Kamoa-Kakula commenced commercial production on July 1, 2021 and with the addition of the Phase 3 concentrator, which achieved commercial production in August 2024, the total copper production capacity is projected to surpass 600,000 tonnes per annum, establishing Kamoa-Kakula as the world's third-largest copper mine.

Download Integrated Development Plan

$2.70 Billion

Record annual revenue recognized in 2023

600kt

Estimated annual copper production following the Phase 3 expansion

393,551

Tonnes of copper produced in 2023

425kt - 450kt

Kamoa-Kakula's 2024 copper production guidance

18,655 kt

Contained Copper - Probable Mineral Reserve

$1.45

Kamoa-Kakula 2023 cash cost per lb. copper

The Kamoa-Kakula Copper Mine — a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of Congo (20%) — is a very large, near-surface, flat-lying, stratiform copper deposit with adjacent prospective exploration areas within the Central African Copperbelt, approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of the provincial capital of Lubumbashi.

Kamoa-Kakula began producing copper concentrates in May 2021 and began commercial production on July 1, 2021. On June 10, 2024 first concentrate production from the Phase 3 concentrator was achieved, months ahead of schedule.  The Phase 3 concentrator expansion reached commercial production early in Q3, 2024 and is expected to boost production to over 600,000 tonnes of copper per annum, making Kamoa-Kakula the largest copper mine on the African continent.

Kamoa-Kakula’s 500,000-tonne-per-annum on-site, direct-to-blister copper smelter and the refurbishment of Turbine #5 at the Inga II hydroelectric facility are advancing on schedule. Construction completion of the smelter is expected by the end of 2024, and Turbine #5 by Q1 2025.

Kamoa-Kakula is powered by clean, renewable hydro-generated electricity and is projected to be among the world’s lowest greenhouse gas emitters per unit of metal produced, as confirmed by a 2020 independent audit performed by Hatch Ltd., of Mississauga, Canada. The Kakula Mine will have one of the most favourable environmental footprints of any tier-one copper mine worldwide. Along with a relatively small surface footprint, approximately 55% of the mine’s tailings will be pumped back into underground workings. Ivanhoe Mines has pledged to achieve net-zero operational greenhouse gas emissions (Scope 1 and 2) at the Kamoa-Kakula Copper Complex.

Phase 3 Concentrator

Kamoa-Kakula’s Phase 3 concentrator expansion completed ahead of schedule in May 2024, with first concentrate reported on June 10, 2024. Phase 3 will boost annualized production to approximately 600,000 tonnes copper.

2023 Pre Feasibility Study assess an increase in production capacity

Kamoa-Kakula's 2023 PFS evaluates a staged increase in production capacity Kamoa-Kakula from the current nominal throughput rate of 7.6 Mtpa up to a total of 19.2 Mtpa by 2030.

Mine life extension to 42 years

The Kamoa-Kakula 2023 preliminary economic assessment (PEA) projects a nine-year mine life extension of the Kamoa-Kakula Copper Complex, in addition to the Kamoa-Kakula 2023 pre-feasibility study of 33 years. This case includes the addition of four new underground mines in the Kamoa area (called Kamoa 3, 4, 5 and 6) to maintain the overall production rate of up to 19.2 Mtpa.

Technical Reports

View document library
Kamoa-Kakula Integrated Development Plan 2023
Kamoa-Kakula Integrated Development Plan 2020, October 2020
Kamoa-Kakula 2020 Resource Update, March 2020
Kamoa-Kakula 2019 Integrated Development Plan, March 2019
Kamoa-Kakula 2018 Resource Update, March 2018

Recent Press Releases

View all press releases
Ivanhoe Mines Issues 2023 Fourth Quarter and Annual Financial Results, Overview of Construction and Exploration Activities
Ivanhoe Mines recognized profit of $303 million, record normalized profit of $388 million and record adjusted EBITDA...
Read more
Ivanhoe Mines Provides 2023 Production Results and 2024 Production Guidance for the Kamoa-Kakula Copper Complex
Kamoa-Kakula produced 393,551 tonnes of copper in concentrate in 2023, within guidance Year-over-year copper production increased...
Read more